Restoration of Orangi Nallah Project
As per NED University Map ID’s (Storm Water Drain)
Length of Orangi Nallah as per NED University Map ID
Total Length of Orangi Nallah
11,287 Meters / 11.287 Kilometers
Total Length Both Sides of Orangi Nallah
22,574 Meters / 22.574 Kilometers
Total Intercepting Units
1,703
Number of Units Above to 30% Eligible for Compensation
1,127
Detail of Both Sides
(Structure IDs Numbering & Marking of Hard Encrochment)
Completed From 15-02-2021 TO 19-02-2021
District West
Zero Point Pakistan Bazar
Banaras
Area Covered
Left Bank
5,300 Meters / 5.3 Kilometers
Right Bank
5,300 Meters / 5.3 Kilometers
District Keamari
Gharib Nawaz Colony Layari Express Way
Banaras
Area Covered
Left Bank
—–
Right Bank
5,987 Meters / 5.987 Kilometers
District Central
Kashmiri Mohallah Layari Express Way
Bangash Colony
Area Covered
Left Bank
5,987 Meters / 5.987 Kilometers
Right Bank
—–
Restoration of Mehmoodabad Nallah Project
Storm Water Drain - Pilot Project
Coordination Committee

NDMA
National Disaster Management Authority

N.E.D.
Nadirshaw Edulji Dinshaw University

Sindh Police
District Administration - Police & Law Enforcement Agencies

KMC
Municipal Services Katchi Abadies Anti-Encroachment City Warden
Staff Engagement
Multiple Meeting Were Held To Streamline The Execution Of Anti-encroachment Drive On Mehmoodabad Nallah (Strom Water Drain)
Mehmoodabad Nallah Encroachment Plan As Per N.E.D Map ID’s
Survey And Collection Of Data Of Each House Hold Mehmoodabad Nallah As Per N.E.D Map ID’s
Joint Teams Of Kmc Katchi Abadies, Land Kmc & District Administration Conducted Survey And Collect Relevant Data Of Each House Hold.
Joint Demarcation Of Mehmoodabad Nallah As Per N.E.D Map ID's
Co-ordination team demarcate and marked id’s on affected structure as per ned map ID's dated: 24-12-2020.
Final Execution Of Anti-encroachment Drive On Mehmoodabad Nallah - Strom Water Drain
Dated: 04-01-2021
Restoration of Gujjar Nallah Project
As per NED University Map ID’s (Storm Water Drain)
Geographical Outlook of Gujjar Nallah (Storm Water Drain)
The Gujjar Nala is Mega Project having length about 25 Kilometers (both sides) starts from Zero Point New Karachi, Nallah Stop, passing through New Karachi & Ali Muhammad Goth, Shafique More, Buffer Zone Gulberg, Samanabad, North Nazimabad, Nazimabad, Liaquatabad, Teen Hatti (Lyari Expressway).
There exist massive encroachments on both sides.
Co-ordianation Committee
Joint Demarcation of Gujjar Nallah as per NED Map ID. The Co-ordiantion team demarcate and marked ID’s on affected structure.

NDMA
National Disaster Management Authority

N.E.D.
Nadirshaw Edulji Dinshaw University

Sindh Police
District Administration - Police & Law Enforcement Agencies

KMC
Municipal Services Katchi Abadies Anti-Encroachment City Warden

Gujjar Nallah Demarcation as per NED Map ID.
Gujjar Nallah Drain Design Parameters (Liberal) As per NED University Map ID's
S.No. | Section(To) | Section(From) | Section Length (m) | Proposed Width of Drain (ft) | Landmarks |
---|---|---|---|---|---|
1 | 0+000 | 0+414 | 414 | 35 | Noorani Masjid Sector 11-E and Godhra Road |
2 | 0+415 | 2+483 | 2068 | 40 | Shafiq Mor |
3 | 2+484 | 4+159 | 1675 | 50 | Cafe Piyala, People's Chowrangi |
4 | 4+160 | 6+081 | 1921 | 60 | Jamia Masjid Ghousia, Landi Kotal Chowrangi |
5 | 6+082 | 6+940 | 858 | 70 | Near Dental College N Block |
6 | 6+941 | 7+202 | 261 | 75 | Near Zafar House Bus Stop |
7 | 7+203 | 12+549 | 5344 | 80 | Liyari Expressway |
Progress
On the directives of the Metropolitan Commissioner KMC, Katchi Abadis Department, KMC, the work of structure ID’s numbering & marking/demarcation of hard encroachment at Gujjar Nallah site as per NED University Map ID’s has also done on 31-01-2021 with the coordination of Additional Deputy Commissioner, Karachi Central/Assistant Commissioner concerned along with Police and City Warden & staff of Assistant Commissioner Office is also collecting Data of affectees as per NED Map ID’s.
Detail of Area (Marking of Encroachment)
Completed From 27-01-2021 TO 31-01-2021
S.No. | Date | Distance Covered | Section (From) | Section (To) |
---|---|---|---|---|
1 | 27/01/2021 | 1500 Meters (Each Side) | (0 Point Noorani Masjid, Sector 11-E, near Godhra) | Godhra |
2 | 28/01/2021 | 3000 Meters (Each Side) | (Godhra stop near CNG Station) | Café Pyala |
3 | 29/01/2021 | 3500 Meters (Each Side) | Café Pyala | Zia Uddin Puliya |
4 | 30/01/2021 | 2000 Meters (Each Side) | Zia Uddin Puliya | DMC Central (Sir Shah Suleman Road) |
5 | 31/01/2021 | 2500 Meters (Each Side) | DMC Central (Sir Shah Suleman Road) | Teen Hatti |
Press Release for Removal of Encroachment on Gujjar Nallah

KMC - Anti Encroachment Press Release
The Express Tribune – 31 January 2021

KMC - Anti Encroachment Press Release
The Express Tribune – 31 January 2021

KMC - Anti Encroachment Press Release
The Express Tribune – 31 January 2021
Execution Of Removal Hard Operation And Distribution Of Compensation Cheques Amongst The Affectess Of Gujjar Nallah
18-02-2021 To Till Date
Re-survey Comprehensive Report
Restoration Of Gujjar Nallah Project As Per Ned University Map ID’s
(District Central - Strom Water Drain)
From 18-02-2021 To 07-12-2021
Length Of Gujjar Nallah As Per Ned University Map Id
Total Length of Gujjar Nallah
12,550 Meters / 12.55 Kilometers
Remaining Length of Gujjar Nallah
Nil Meters / Nil Kilometers
Total Distance Covered
12,550 Meters / 12.55 Kilometers
Detail Of Intercepting Units
Total Intercepting Units
4,058
Number of Units Above to 30% Eligible for Compensation
3,137
From 08-02-2021 TO 13-02-2021
Category | Details |
---|---|
Soft Encroachment | Thallahs, Patharas, Sun Sheds, Damaged Vehicles, Afghani Garbage (Kachra) Collection Points & Cattle Bara’s used commercially have been removed |
Total Encroachments Removed | 2,870 Soft Encroachments |
From 18-02-2021 TO 06-12-2021
Weight | 28,064 Tons |
---|
Total IDs | Total IDs Demolished | Total IDs Partially Demolished | Remaining IDs to be Demolished |
---|---|---|---|
4,058 | 4,058 | Nil | Nil |
As per Site Inspection all ID’s has been removed, further during the re-survey FWO point out few demolishing work which will carried out after approval from Competent Authority.
Comprehensive Report
Restoration Of Mehmoodabad Nallah Project As Per Ned University Map ID’s
(District Central - Strom Water Drain)
From 15-12-2020 To 26-03-2021
Length Of Mehmoodabad Nallah As Per Ned University Map Id
Total Length of Mehmoodabad Nallah
3,500 Meters / 3.55 Kilometers
Remaining Length of Gujjar Nallah
Nil Meters / Nil Kilometers
Total Distance Covered
3,500 Meters / 3.5 Kilometers
Detail Of Intercepting Units
Total Intercepting Units
238
Number of Units Above to 30% Eligible for Compensation
56
SUB-DIVISION | TOTAL CHEQUES RECEIVED | TOTAL CHEQUES DISTRIBUTED | CHEQUES UNDER CORRECTION | CHEQUES UNDER CANCELLATION | CHEQUES IN HAND | TOTAL SOFT ENCROACHMENT REMOVED (04-01-2021 to 10-01-2021) |
---|---|---|---|---|---|---|
Ferozabad Sub-Division (District East) (1st Installment) | 59 | 57 | 0 | 2 | 0 | Soft Encroachment (thallahs, patharas, sun sheds, damaged vehicles, Afghani garbage collection points & cattle bara’s removed) |
1170 Soft Encroachment | ||||||
Ferozabad Sub-Division (District East) (2nd Installment) | 49 | 47 | 0 | 0 | 2 | TOTAL GARBAGE/DEBRIS REMOVAL (11-01-2021 to 10-02-2021) |
Weight: 12,944 Tons | ||||||
Total | 108 | 104 | 0 | 2 | 2 | |
Total No. of Structures Removed as per NED University ID | ||||||
Current Status of Removal Operation | ||||||
Total 238 IDs have been removed completely | ||||||
Total Remaining IDs: Nil |